Fandango

Timeline

Project initiation completed

This milestones will be reached throughot the following deliverables:

  • D1.1 Management Website
  • D1.2 Data Management Plan
  • D1.3 Quality Plan
  • D2.1 Data lake integration plan
  • D7.1 Development of project website

Work packages WP1, WP2 & WP7

Engineering

June 2018

First pilot implemented

This milestones will be verified throughot the following deliverables:

  • D1.4 1st Interim Periodic Reports
  • D2.2 Data Interoperability and data model design
  • D6.1 Pilots execution and evaluation plans
  • D7.2 Dissemination Plan

Work packages WP1, WP2, WP6 & WP7

VRT

December 2018

First pilot validated

This milestones will be verified through the following deliverables:

  • D2.3 Technical requirements (platform and service requirements)
  • D3.1 Data model and components
  • D3.2 Lightweight data shipping components development
  • D3.3 Pre- processing set of tools
  • D3.4 Ground truth development for FANDANGO system assessment
  • D4.1 Spatio- temporal analytics and out of context fakeness markers prototypes
  • D4.2 Multilingual text analytics for misleading messages detection prototypes
  • D4.3 Copy-move detection on audio-visual content prototypes
  • D4.4 Source credibility scoring, profiling and social graph analytics prototypes
  • D4.5 Machine learnable scoring for fake news decision making prototypes
  • D6.2 First iteration piloting and validation report
  • D8.1 Market Analysis and preliminary business requirement
  • D8.2 Application areas business requirements and preliminary exploitation plan

Work packages WP2, WP3, WP4, WP6 & WP8

Siren Solutions

December 2019

Finishing of the second round of pilots

This milestones will be verified through the following deliverables:

  • D4.6 Software updates of the modules and prototypes
  • D6.3 Second iteration piloting and validation report

Work packages WP4 & WP6

CERTH

December 2020

Project completed

This milestones will be achieved through the following deliverables:

  • D7.3 Impact Report • Final Exploitation plan and technology uptake
  • Report replicability of the solution
  • Final Project Progress Report

Work packages WP1, WP7 & WP8

Engineering

December 2020